At any time, you can modify or add the resource(s) assigned to a work order in the Calendar, in a number of ways.
We offer two ways to view this article, depending on your preferences:
🎥 Video capsule
📙 Step-by-step guide
Calendar
Using your mouse, drag & drop the estimated duration of the work order on the Calendar to the resource to which you want to assign the work order.
Calendar
Click on the work order tile to open it
In the Resource section of the work order, click on the 🔽 to select or add the resource on the list.
Planner
On the Planner's Display button , check the Resource column
Click below the Resource column for each work order and
modify-add the desired resource(s)